Project Nam Hinboun Downstream HPP
OperatorRasita Power Co. Ltd
Commercial Operation2022
Installed Capacity15 MW
Net HeadLow head
Turbines2 x 7.5 MW Bulb Turbines
Catchment Nam Hinboun river and THPC main power station outflow
Dam TypeConcrete Gravity
Project TypeRun of River
Websitehttps://www.facebook.com/RasitaLao
Detail In the dry season, this project benefits from being downstream of the Thuen Hinboun Project receiving the same water for power production that already flowed through the THPC power station. In the flood season, backwater effects from the Mekong mean there is not enough head for production